Factory licence in Lebanon: categories, documents and steps to open or regularise a plant
Lebanon’s Ministry of Industry licenses factories in five categories. Categories 1 to 3 need a licence to build, then one to operate; the law gives the minister two months to decide.
2 months
A factory licence in Lebanon is issued by the Ministry of Industry according to the plant’s category, from 1 (serious hazard) to 5 (no harm): categories 1 to 3 need two licences, one to build (إنشاء) and one to operate (استثمار), and the ministry also publishes a single combined form for categories 3, 4 and 5.
The law sets the clock. The minister must decide on a licence to build within two months of filing, and on a licence to operate within one month (Decree 8018 of 12 June 2002, Article 13). Delays actually observed by applicants were not found for this article.
Fees are the weak point. The ministry’s document sheets, dated November 2011, still list LBP 100,000 to 800,000. A decree numbered 14503, reported by the press on 31 December 2024, raised the verification fee to LBP 10 to 40 million, or about USD 112 to 447 at LBP 89,500 per dollar, the Banque du Liban rate since February 2024. Confirm the amount at the counter.
The five categories
| Category | Definition (Decree 8018, Art. 3) | Route (ministry forms) | Verification fee (Decree 14503, reported) |
|---|---|---|---|
| 1 | Serious hazard to the environment and public health; must be kept away from housing | Build, then operate | LBP 40 million (about USD 447) |
| 2 | Hazard; need not be kept away from housing, but may operate only with protective measures | Build, then operate | LBP 30 million (about USD 335) |
| 3 | Limited hazard; subject to special rules | Build, then operate, or combined form | LBP 20 million (about USD 223) |
| 4 | Minor harm; subject to special rules | Combined form | LBP 15 million (about USD 168) |
| 5 | No harm to the environment or public health | Combined form | LBP 10 million (about USD 112) |
The category of each activity is set by the table annexed to Decree 5243 of 5 April 2001, by activity code. That table was not read for this article: check your code with the licensing department before you sign a lease or draw plans.
The category also decides where you may build. Outside zoned areas, a category 1 plant needs a plot of at least 15,000 m², a category 2 plant 5,000 m² (Article 19), at least 1,000 metres from protected sites and 250 metres from the main rivers (Article 20). On irrigated or prime farmland, only agro-industrial plants are allowed (Article 5).
Step 1: the licence to build
The ministry’s document sheets for categories 1, 2 and 3 ask for:
- The application form addressed to the Ministry of Industry.
- A copy of the applicant’s identity card, or work permit for a foreign national.
- For a company: its commercial notice and registration certificate.
- A notarised power of attorney if the owner does not file in person.
- A 1:2,000 site plan showing the neighbouring plots and vehicle access to the public road.
- Building plans, and a layout of machines and equipment, especially in the production area, stamped by an engineer.
- A land registry statement, and a zoning and alignment statement less than three months old.
- A lease certified by the municipality, a title deed, or a notarised investment contract or permission.
- A municipal clearance (and a tax clearance if the applicant owns the land).
- A full study of the manufacturing process and of how wastewater and solid waste will be disposed of without polluting surface or ground water.
- Categories 1 and 2 only: a pledge under Article 17(6) of Decree 8018.
Make four copies: one goes first to the municipality, against a numbered receipt; three go to the ministry with the original. In Beirut and Mount Lebanon, files go to the Industrial Licensing Department, 4th floor of the ministry’s central administration. Elsewhere, they go to the regional offices in Zahle, Tripoli, Sidon or Nabatieh.
Legal deadlines: the municipality gives its opinion within one month, or is deemed to agree (Article 11); the licensing committee within six weeks (Article 12); the minister within two months (Article 13). If no decision comes, the applicant may ask for it in writing; silence for a further month counts as tacit approval (Article 13).
Step 2: the licence to operate
Once the plant is built as the first licence requires, you file three copies of: the application, the licence to build, the occupancy permit with plans, photographs and the machine layout. The committee inspects the site and, if it matches, reports within two weeks; if not, it grants extra time to fix the gaps (Article 26).
This stage costs half the verification fee: LBP 5 to 20 million (about USD 56 to 223) under Decree 14503 as reported. The 2011 sheets add a fiscal stamp of LBP 750,000; its current amount was not confirmed.
Ministerial Decision 14/1 of 24 January 2012 lists the general conditions, including fire and accident insurance, sorted waste, wastewater to the sewer or a septic tank, a generator in a separate room with filters, protective equipment and mandatory Lebanese standards.
A licence lapses if production does not start in time: within the period set in the licence, never under three years, for categories 1 and 2; within two years for categories 3, 4 and 5 (Article 33).
Regularising a plant already running
Established: under Article 34, if an unlicensed plant harms its neighbours or public health, the minister may order it to regularise within six months; otherwise it is closed, after the committee and the municipality have given their opinion. The general deadline for existing plants in Article 39 expired on 31 December 2006.
Reported: in February 2026, the ministry issued Circular 13/1 asking unlicensed industrial establishments to file a licensing or regularisation request with the ministry or its regional office by 15 April 2026 (Lebanon Debate, 17 February 2026). What happens to late files was not confirmed.
Food plants: a second registration
Any food factory that sells on the Lebanese market or exports must also register with the Ministry of Agriculture to obtain a health numbering certificate (شهادة ترقيم صحي). The file goes to the regional agriculture service. It includes the operating licence and the industrial certificate issued by the Ministry of Industry, and a chamber membership certificate for exporters. Inspectors check good manufacturing practice and Lebanese standards 656 (food hygiene), 605 (HACCP) and 654 (frozen food).
The industrial certificate has its own form on the Ministry of Industry website; its validity and uses were not checked.
What is not confirmed
- Decree 14503 and its fees: known from a press report (31 December 2024); its date and Official Gazette text were not read, and the ministry sheets still show the 2011 amounts.
- The current fiscal stamp on the operating licence.
- Actual processing times: only the legal maximums are known.
- The category of a given activity: the Decree 5243 table was not read.
- Circular 13/1 of 2026: known from the press; its text and the treatment of late files were not read.
- The Ministry of Agriculture decision behind food plant registration (reported as 1/950): not found on the pages read; fees and timing not published there.
- The exchange rate: the Banque du Liban page returned an error (403) when checked.
Sources
- Ministry of Industry, « النماذج الخاصة بالتراخيص الصناعية (Industrial licence forms) », accessed 13/10/2026
- Ministry of Industry, « المستندات التي يجب ارفاقها بطلب الترخيص لإنشاء صناعة من الفئة الاولى أو الثانية », 14/11/2011
- Ministry of Industry, « المستندات التي يجب ارفاقها بطلب الترخيص لإنشاء صناعة من الفئة الثالثة », 14/11/2011
- Ministry of Industry, « المستندات التي يجب ارفاقها بطلب الترخيص بإنشاء و إستثمار صناعة من الفئات الثالثة، الرابعة و الخامسة », 14/11/2011
- Ministry of Industry, « المستندات التي يجب ارفاقها بطلب الترخيص لإستثمار صناعة بعد الإنشاء », 14/11/2011
- Ministry of Industry, « قرار رقم 14/1: الشروط العامة للترخيص للمؤسسات الصناعية », 24/01/2012
- Decree No. 8018 of 12/06/2002, Official Gazette No. 37 of 27/06/2002, « تحديد اصول واجراءات وشروط الترخيص بانشاء المؤسسات الصناعية واستثمارها », Lebanese University legal text, accessed 13/10/2026
- Lebanon Debate, « تعديلٌ هام في شروط ترخيص المؤسسات الصناعية », 31/12/2024
- Lebanon Debate, « وزارة الصناعة تتحرك: إنذار أخير للمؤسسات غير المرخّصة », 17/02/2026
- Ministry of Agriculture, « آلية تسجيل مصانع الأغذية (Food factory registration) », accessed 13/10/2026
- Ministry of Agriculture, « الصناعات الغذائية: المعاملات الإدارية (Agro-food industries: administrative procedures) », accessed 13/10/2026
Verified on 13.10.2026.
Sources
- Ministry of Industry, « النماذج الخاصة بالتراخيص الصناعية (Industrial licence forms) », accessed 13/10/2026 : industry.gov.lb/FormsApplications/PermitFormPage
- Ministry of Industry, « المستندات التي يجب ارفاقها بطلب الترخيص لإنشاء صناعة من الفئة الاولى أو الثانية », 14/11/2011 : industry.gov.lb/getattachment/FormsApplications/PermitFormPag…
- Ministry of Industry, « المستندات التي يجب ارفاقها بطلب الترخيص لإنشاء صناعة من الفئة الثالثة », 14/11/2011 : industry.gov.lb/getattachment/FormsApplications/PermitFormPag…
- Ministry of Industry, « المستندات التي يجب ارفاقها بطلب الترخيص بإنشاء و إستثمار صناعة من الفئات الثالثة، الرابعة و الخامسة », 14/11/2011 : industry.gov.lb/getattachment/FormsApplications/PermitFormPag…
- Ministry of Industry, « المستندات التي يجب ارفاقها بطلب الترخيص لإستثمار صناعة بعد الإنشاء », 14/11/2011 : industry.gov.lb/getattachment/FormsApplications/PermitFormPag…
- Ministry of Industry, « قرار رقم 14/1: الشروط العامة للترخيص للمؤسسات الصناعية », 24/01/2012 : industry.gov.lb/getattachment/FormsApplications/PermitFormPag…
- Decree No. 8018 of 12/06/2002, Official Gazette No. 37 of 27/06/2002, « تحديد اصول واجراءات وشروط الترخيص بانشاء المؤسسات الصناعية واستثمارها », accessed 13/10/2026 : dgu.gov.lb/8018_2002.pdf
- Lebanon Debate, « تعديلٌ هام في شروط ترخيص المؤسسات الصناعية », 31/12/2024 : lebanondebate.com/article/678830-article
- Lebanon Debate, « وزارة الصناعة تتحرك: إنذار أخير للمؤسسات غير المرخّصة », 17/02/2026 : lebanondebate.com/article/791307-%D9%88%D8%B2%D8%A7%D8%B1%D8%…
- Ministry of Agriculture, « آلية تسجيل مصانع الأغذية (Food factory registration) », accessed 13/10/2026 : agriculture.gov.lb/Subjects/Rural-Development-and-Natural-Res…
- Ministry of Agriculture, « الصناعات الغذائية: المعاملات الإدارية (Agro-food industries: administrative procedures) », accessed 13/10/2026 : agriculture.gov.lb/Subjects/Rural-Development-and-Natural-Res…